MOQ, Reel Quantity or Order Multiple? How to Compare Two Component Quotes

Need to source components?

Share the full manufacturer part number, quantity and any sourcing or documentation requirements.

You need 600 components. One supplier quotes $0.90 per piece and requires a full reel of 1,000. Another quotes $1.10 and will supply 600 on cut tape. The first quote has the lower unit price. The second has the lower parts total for this order.

Check which quantity the supplier will accept

MOQ is the minimum quantity the supplier will accept for the line. Reel quantity is the number of pieces in a reel. It limits the purchase quantity when the quote requires full reels. An order multiple is the increment the supplier accepts, such as whole multiples of 100 pieces. Confirm all three on the quotation, along with whether the supplier will cut tape or re-reel the parts.

Before comparing prices, match the complete manufacturer part number, including its suffix, the currency and the delivery terms. Confirm that each packing option meets your receiving and assembly requirements.

Compare what you will pay for 600 pieces of demand

Both illustrative quotes below cover the same orderable part and use US dollars and the same delivery terms. Quote A requires one full reel. Quote B accepts an order for exactly 600 pieces on cut tape.

ComparisonQuote AQuote B
Packing conditionFull reel only (1,000 pcs)Cut tape accepted
Required quantity600 pcs600 pcs
Minimum purchase for this order1,000 pcs600 pcs
Unit price$0.90$1.10
Parts total$900$660
Surplus400 pcs0 pcs
Illustrative comparison in US dollars. Parts totals exclude packing fees, freight and taxes.

Quote B costs $240 less in parts for the initial order. If the feeder requires a reel, check whether cut tape is acceptable or ask for the fee and lead time to re-reel it. Also check when each quantity can ship and whether you can use the 400 surplus pieces on a later build. Compare freight, taxes and packing fees separately.

Calculate the order multiple separately

A second illustration uses a demand of 610 pieces, a 500-piece MOQ and order quantities in whole multiples of 100. The 500-piece minimum is already met, so the next valid quantity is 700 pieces. That leaves 90 pieces above demand. Confirm which quantities the supplier accepts if the quote describes the increment differently.

Record comparable quantities on the BOM

Record the demand quantity, lowest acceptable order quantity, unit price, parts total and surplus on separate lines or columns. Ask each supplier to confirm the MOQ, the accepted order quantities, the packing being offered, packing fees and the earliest ship date for that quantity.

Use the BOM RFQ template and example to send each supplier the same purchasing requirements and compare their replies line by line.

Send Inquiry

Tell us what you need